
Spanish Peaks Montage, Big Sky
SP HOTELS LLC
Welcome to the Montage at Big Sky construction page. This site is intended for construction-related information. Visit this page for important work updates, news alerts, feature stories, and contact information.
About the Project
In September 2018, Suffolk and the development team for the Spanish Peaks Mountain Club broke ground on this $400 million, 518,000 square-foot project. Visitors seeking adventure in Montana and Yellowstone National Park will be able to take advantage of the ultra-luxury resort’s 150 guest rooms, 39 residences, restaurant, bar, lounge, bowling alley, pool, youth programming, and Spa Montage. The facility will also boast 12,870 square feet of meeting and event space.
For those looking to get outside, Montage Big Sky will have ski-in, ski-out access to 5,800 skiable acres at Big Sky Resort - the second largest ski resort in the United States by acreage - and access to Spanish Peaks Mountain Club’s 18-hole golf course. The resort is scheduled to open in late 2021.

Project Milestones
Construction Start Date: 9/4/2018
Demo of existing building: 9/17/2018
First Concrete Pour: 12/17/2018
South Tower Crane: 4/4/2019
First Busing: 5/13/2019
MEP Rough: 2/4/2019
First Steel Column: 6/3/2019
Second North Tower: 6/22/2019
Completion of first level of concrete walls: 7/23/2019
First concrete Deck pour: 7/24/2019
First Drilled Piers: 9/03/2019
First Steel Roof: 9/18/2019
Last Concrete wall pour: 10/22/2019
Drilled Piers complete: 11/8/2019
Temporary Hoist installed: 11/26/2019
First Window Install: 1/29/2020
Final Concrete Deck Pour on the South Side of the building: 2/13/2020
Chimney Cap installed on North Side 5/14/2020
Final Concrete Deck Pour on the North Side of the Building 8/1/2020
Steel Topping off 8/13/2020
Hotel 2025 Mockup reviewed at Approved 8/17/2020
Roof in Area 3 dried in 11/15/2020
Condo 13 Mockup Complete 11/20/2020
Percent Complete as of November 30, 2020: 67%
Construction Updates
Week of 5.25.20 - 5.29.20
Site Closed for Memorial Day 4/25
Backfill to top of grade in Area 3 4/26-4/30
Steel decking and detailing 4/16-4/30
Install of exterior stone 4/26-4/30
Install of Roof shingles north side of building 4/26-4/30
Concrete Pour Area 4 Level 4 5/28
Week of 6.1.20 - 6.5.20
Start of Westside ski beach grading 6/1-6/5
Erecting zones 52-54 6/1-6/5
Steel decking and detailing 6/1-6/5
Concrete Pour Area 4 level 5 6/4
Box walk for Condo 13 6/3
Week of 6.15.20 - 6.19.20
Install of windows Area 2A West 6/15-6/19
Install if exterior stone 6/15-6/19
Exterior framing Area 2 West 6/15-6/19
Electrical rough in Level 3 6/15-6/19
Week of 6.22.20 - 6.26.20
Concrete Pour Area 3 Level 2 6/25
Steel decking and detailing 6/22-6/25
Exterior framing Area 2 East 6/22-6/25
Close up of Hotel rooms 6/22-6/25
Project Gallery
Joel Nickel
Vice President & Executive Project Director
Doug Brinkman
General Superintendent
Ryan Wilson
Senior Project Manager

Luke Regan
Safety Manager
Max Rodgers
Project Controller
Amanda Hamstra
Project Administrator
Joel Wilson
MEP Superintendent
Tom Cobb
Sr. Superintendent
Jeremy Perez
Superintendent
Dylan Schultz
Superintendent
Cam MacDonald
Assistant Superintendent
Tyler Hough
Assistant Superintendent
Nate Hamstra
Project Manager
Tyler Clements
MEP Manager
Caitlin Tamposi
Project Manager
Todd Rossier
Project Manager
Harrison Lyons
Assistant Project Manager
Spencer Schmidt
Assistant Project Manager
Ted Durkin
Assistant Project Manager
Oliver Lowe
Project Engineer and Digital Content Coordinator