Spanish Peaks Montage, Big Sky

SP HOTELS LLC

Welcome to the Montage at Big Sky construction page. This site is intended for construction-related information. Visit this page for important work updates, news alerts, feature stories, and contact information.

 

ABOUT THE PROJECT

In September 2018, Suffolk and the development team for the Spanish Peaks Mountain Club broke ground on this $400 million, 518,000 square-foot project. Visitors seeking adventure in Montana and Yellowstone National Park will be able to take advantage of the ultra-luxury resort’s 150 guest rooms, 39 residences, restaurant, bar, lounge, bowling alley, pool, youth programming, and Spa Montage. The facility will also boast 12,870 square feet of meeting and event space. 

 

For those looking to get outside, Montage Big Sky will have ski-in, ski-out access to 5,800 skiable acres at Big Sky Resort - the second largest ski resort in the United States by acreage - and access to Spanish Peaks Mountain Club’s 18-hole golf course. The resort is scheduled to open in late 2021.

PROJECT MILESTONES

Construction Start Date:  9/4/2018

Demo of existing building: 9/17/2018

First Concrete Pour:  12/17/2018

South Tower Crane: 4/4/2019

First Busing: 5/13/2019

MEP Rough: 2/4/2019

First Steel Column:  6/3/2019

Second North Tower: 6/22/2019

Completion of first level of concrete walls: 7/23/2019

First concrete Deck pour: 7/24/2019

First Drilled Piers: 9/03/2019

First Steel Roof: 9/18/2019
Last Concrete wall pour: 10/22/2019

Drilled Piers complete: 11/8/2019
Temporary Hoist installed: 11/26/2019

Percent Complete as of November 29, 2019: 25%

 
CONSTRUCTION UPDATES

Week of 12/16/19 - 12/20/2019

  • Install sprinkler pipe in hotel area
    12/16-12/20

  • Service pads for main transformer installed 12/16-12/19

  • Exterior Framing Area 1 Level 5 and 6 12/16-12/20

  • Concrete Pour Area 2 Level 5  12/19

  • Steel Erecting 12/16-12/20

Week of 12/8/19 - 12/13/2019

  • Pier Cap Grade Beam Excavation 12/8-12/13

  • Fire Alarm Conduit Install 12/8-12/13

  • Interior Framing Area 1 Level 2 and 3 12/8-12/13

  • Install Main Gas risers in Hotel area 12/8-12/13

  • Steel Erecting 12/8-12/13

Week of 12/23/19 - 12/28/2019

  • Install duct work Area 1 Level 1 12/23, 12/26-12/28

  • Interior framing Area 1 Level 5 and 6 12/23, 12/26-12/28

  • Fireproofing Area 2 Level 4 12/23, 12/26-12/28

 
PROJECT GALLERY
 
MEET THE CONSTRUCTION TEAM
 

Joel Nickel

Vice President & Executive Project Director

Doug Brinkman

General Superintendent 

Ryan Wilson

Senior Project Manager

Luke Regan

Safety Manager

Max Rodgers

Project Controller

Amanda Hamstra

Project Administrator

Joel Wilson

MEP Superintendent

Tom Cobb

Sr. Superintendent 

Jeremy Perez

Superintendent

Dylan Schultz

Superintendent

Cam MacDonald

Assistant Superintendent

Tyler Hough

Assistant Superintendent

Nate Hamstra

Project Manager

Tyler Clements

MEP Manager

Caitlin Tamposi

Project Manager

Todd Rossier

Project Manager

Harrison Lyons

Assistant Project Manager

Spencer Schmidt

Assistant Project Manager

Ted Durkin

Assistant Project Manager

Oliver Lowe

Project Engineer and Digital Content Coordinator

 
  • Black Facebook Icon
  • Black LinkedIn Icon
  • Black Twitter Icon
  • Black Instagram Icon